APS Facilities Design & Construction




CURRENT PROJECTS



Jimmy Carter MS Projects

Photos for the week of 05-08-2008
Click for photo archives


Project Description HVAC Project
Budget $60,000
Project Status Study
Project Number 0445.0009.41507
Project Manager David Robertson
Architect/Engineer WH Pacific O/E
Design Doc Appr Date N/A
Substantial Complete Date
Warranty Inspect Date


Project Description Phase II Classroom Addition
Budget $2,992,462
Project Status Warranty
Project Number 0445.0001.44506
Project Manager John Mazzola
Architect/Engineer Fanning Bard Tatum
Design Doc Appr Date 8/15/06
Substantial Complete Date 10/1/08 E Bldg. 11/19/08 D Bldg.
Warranty Inspect Date 9/1/09 E Bldg. 10/19/09 D Bldg.