APS Capital Master Plan 06-13 Projects for 351 CORRALES ES

Proj. No. Code Project Name Total
Project
Budget
PSCOC
Awards
Accepted
APS
Budget
HB 33 Projects Approved by Voters in February 2005
351.2 5.02.C01.1. Addition to and Refurbishing of the Cafeteria $493,512 $0 $493,512
351.7 3.06.E02.1. Replacement of Courtyard Dying Trees $22,774 $0 $22,774
351.9 4.14.A03.1.1. HVAC Humidity Resolution $43,443 $0 $43,443
351.11 4.14.A02.1. Study CMU Cracking on Gym and E. End Old Wing $16,202 $0 $16,202
351.80 4.07.G01.1. School Improvement Project $38,630 $0 $38,630
351.81 5.09.A06.1. School-Based Technology Allocation $38,600 $0 $38,600
351.85 2.08.A06.1. Network Infrastructure Upgrades and Replacement $42,314 $0 $42,314
HB 33 06 Projects = 7 Total Budget for HB 33 06 $695,475 $0 $695,475
GO Bond 06 Projects Approved by Voters in February 2006
351.82 5.09.A06.1 School-Based Technology Allocation $19,300 $0 $19,300
GO Bond 06 Projects = 1 Total Budget for GO Bond 06 $19,300 $0 $19,300
GO Bond 06 Supplemental Projects Approved by Voters in September 2006
351.18 4.08.D04.1. Supplemental Roofing Projects $1,005,312 $0 $1,005,312
351.91 6.04.B01.1. Supplemental Contingency Funding for a Fire Suppression System $450,000 $0 $450,000
GO Bond 06 Supplemental Projects = 2 Total Budget for GO Bond 06 Supplemental $1,455,312 $0 $1,455,312
SB 9 Projects Approved by Voters in February 2007
351.5 4.04.A03.2.1. Electrical Upgrade for Old WIngs $144,963 $0 $144,963
351.70 5.09.C07.6. Student/Teacher School Furniture Renewal $48,000 $0 $48,000
351.73 7.05.A03.1.6. Environmental Systems Fund $150,000 $0 $150,000
351.74 7.04.G01.6. Facility Repair and Renewal Fund $9,000 $0 $9,000
351.78 7.05.G01.6. Physical Education Facility Upgrades Fund $10,000 $0 $10,000
351.90 4.08.A06.1. School-Based Technology Infrastructure Allocation $115,200 $0 $115,200
SB 9 08 Projects = 6 Total Budget for SB 9 08 $477,163 $0 $477,163
GO Bond 10 Projects to be Considered by Voters in February 2010
351.83 5.09.A06.1. School-Based Technology Allocation $19,300 $0 $19,300
351.88 4.08.A06.2. Network Equipment Upgrades and Replacement $57,787 $0 $57,787
GO Bond 10 Projects = 2 Total Budget for GO Bond 10 $77,087 $0 $77,087
--------------------------------------------------------------------------------------------------------------------------------------------------
Projects to to be considered with future funding sources
351.3 4.04.C01.2. Refurbish Old North and South Wings $1,064,531 $0 $1,064,531
351.6 2.04.C01.1. Renovate 2 Classrooms for Kindergarten $186,484 $0 $186,484
351.8 2.02.C09.1. Restroom / Storage Addition to Gym $494,852 $0 $494,852
351.10 4.06.E01.1. South Parking Lot Improvements $35,994 $0 $35,994
351.12 2.02.F02.3. Kindergarten Addition $1,170,833 $0 $1,170,833
351.13 4.04.D02.3. Stucco Surface Improvements $111,304 $0 $111,304
351.14 4.08.C04.1.3. Replace Ceiling Tile in the New Wing $90,717 $0 $90,717
351.15 2.06.E06.3. Playground and Site Upgrades $89,791 $0 $89,791
351.16 4.06.E10.1.1. Renovate the Grass Field $88,995 $0 $88,995
351.17 4.08.A04.1. Replace Domestic Water Lines $145,000 $0 $145,000
Future Projects = 10 Total Budget for Future Funding $3,478,501 $0 $3,478,501
Total Projects = 28 Grand Total of Projects Budget $6,202,837 $0 $6,202,837


09/09/10 at 9:15 pm