APS Capital Master Plan 06-13 Projects for 204 ACOMA ES

Proj. No. Code Project Name Total
Project
Budget
PSCOC
Awards
Accepted
APS
Budget
HB 33 Projects Approved by Voters in February 2005
204.2 4.04.C09.1. Restroom Improvements $156,044 $0 $156,044
204.80 4.07.G01.1. School Improvement Project $20,420 $0 $20,420
204.81 5.09.A06.1. School-Based Technology Allocation $20,400 $0 $20,400
204.85 2.08.A06.1. Network Infrastructure Upgrades and Replacement $73,418 $0 $73,418
HB 33 06 Projects = 4 Total Budget for HB 33 06 $270,282 $0 $270,282
GO Bond 06 Projects Approved by Voters in February 2006
204.82 5.09.A06.1 School-Based Technology Allocation $10,200 $0 $10,200
GO Bond 06 Projects = 1 Total Budget for GO Bond 06 $10,200 $0 $10,200
GO Bond 06 Supplemental Projects Approved by Voters in September 2006
204.91 4.06.E01.1. Supplemental Contingency Funding for Playground and Drainage Improvements $125,000 $0 $125,000
GO Bond 06 Supplemental Projects = 1 Total Budget for GO Bond 06 Supplemental $125,000 $0 $125,000
SB 9 Projects Approved by Voters in February 2007
204.70 5.09.C07.6. Student/Teacher School Furniture Renewal $48,000 $0 $48,000
204.90 4.08.A06.1. School-Based Technology Infrastructure Allocation $52,300 $0 $52,300
SB 9 08 Projects = 2 Total Budget for SB 9 08 $100,300 $0 $100,300
GO Bond 10 Projects to be Considered by Voters in February 2010
204.83 5.09.A06.1. School-Based Technology Allocation $10,200 $0 $10,200
204.88 4.08.A06.2. Network Equipment Upgrades and Replacement $30,820 $0 $30,820
GO Bond 10 Projects = 2 Total Budget for GO Bond 10 $41,020 $0 $41,020
--------------------------------------------------------------------------------------------------------------------------------------------------
Projects to to be considered with future funding sources
204.1 2.02.F02.1. Kindergarten Classroom Addition/with Play Lot $1,585,006 $0 $1,585,006
204.3 4.04.A03.2.1. Electrical Upgrades $468,326 $0 $468,326
204.4 4.06.E02.2. Landscaping Improvements $122,508 $0 $122,508
204.5 4.05.C01.2. Classroom Renovations $700,178 $0 $700,178
204.6 4.06.E01.1. Site Improvements $270,812 $0 $270,812
204.7 4.02.F01.2. Kitchen Expansion/Cafeteria Remodel $537,060 $0 $537,060
204.8 2.06.E01.3. Outdoor Amphitheater with Access Ramps $150,450 $0 $150,450
204.9 4.08.D04.2. Roof Replacement $1,096,513 $0 $1,096,513
204.10 4.08.A03.1.1. HVAC - Rebuild West and South Air Washers $215,000 $0 $215,000
204.11 4.08.B02.1. Asbestos Tile Floor $10,000 $0 $10,000
204.12 4.08.C10.1. Window Blind Replacement $30,000 $0 $30,000
204.13 4.06.E10.1.1. Grass Field Irrigation System Upgrade $40,000 $0 $40,000
204.14 4.06.E03.3. Service Drive Improvements $57,662 $0 $57,662
Future Projects = 13 Total Budget for Future Funding $5,283,514 $0 $5,283,514
Total Projects = 23 Grand Total of Projects Budget $5,830,316 $0 $5,830,316